§ 16.40.030.7. Review and fees.  


Latest version.
  • A.

    Final stormwater management plans and calculations shall be submitted by a licensed engineer registered in the State and must be approved by the POD before work may begin on the drainage system. The stormwater management plans shall comply with this section.

    B.

    Final grading and drainage plans shall be approved by the POD. Permits shall not be issued until final grading and drainage plans are approved.

    C.

    No portion of the work may begin on the installation of drainage improvements until plans have been approved by the POD.

    D.

    The City may collect and retain fees for the review and approval of applications. Such fees shall be established by City Council.

(Code 1992, § 16.40.030.7)